Construction Work at Long Island City and Astoria Elementary Schools To Resume: SCA

The new school building for P.S. 384 is going up in Hunters Point in Long Island City (Photo: Queens Post)

Sept. 17, 2020 By Christian Murray

The School Construction Authority, which stopped work on building new schools when COVID-19 took hold in March, will be restarting work on P.S. 384Q in Long Island City, with a completion date of September 2021 still in tact.

The SCA had put the construction of new schools across the city on pause in March, citing the city’s budget constraints as well as COVID-19.

Construction work at some schools will now resume—including P.S. 384Q and an annex at P.S. 2 in Astoria–both slated to open in September 2021.

The middle school, however, on 48th Street in Sunnyside that is scheduled to be completed by September 2022 remains on hold.

“The P.S. 2 addition and the Parcel F school on 57 Ave [P.S. 384Q] are one of several projects that have been unpaused,” said Kevin Ortiz, a spokesperson with the School Construction Authority. “Work will resume in the coming days in order to meet our target opening of Sept 2021 for both.”

Ortiz said that the middle school in Sunnyside remains on pause.

The agency attributes the work stoppages to COVID-19 and the city’s fiscal crisis.

“We were requested by the Mayor’s Office of Management and Budget to pause the majority of our work,” said Benjamin Goodman, a representative for the SCA, at Community Board 2’s monthly meeting on Sept. 3.

The completion date of many schools under construction remains uncertain.

The resumption of work at the new school building in Long Island City comes as a relief to many parents since the new building is expected to accommodate the current students at P.S.384Q, who are currently being taught at an incubator school that was established at 27-35 Jackson Ave in 2018.

A delay would cause significant overcrowding problems since the Jackson Avenue incubator site is not big enough to accommodate the influx of students expected to go to P.S. 384 in the 2021/2022 school year.

Lisa Deller, Community Board 2 Chair, warned Goodman at the CB2 meeting of a domino effect if the completion date is pushed back.

Meanwhile, the P.S. 2 annex, which is going up at the 75-10 21st Ave. school, is also back on track for opening in September 2021.

The $29 million annex will replace a temporary building that currently covers a portion of the school yard. The 3-story annex will include four new Pre-K classrooms, four Kindergarten classrooms and one regular classroom, as well as an art room, music room, exercise room and supervisory offices.

The annex is expected to cater to about 180 students.

Rendering of P.S. 2 annex Courtesy of School Construction Authority

email the author: [email protected]
No comments yet

Leave a Comment
Reply to this Comment

All comments are subject to moderation before being posted.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Recent News

Queens Public Library celebrates Black History Month with nearly 150 programs highlighting Black resistance, culture

Feb. 2, 2023 By Carlotta Mohamed

Throughout February, Queens Public Library will celebrate “Black Resistance” – the theme of its 2023 Black History Month observance – with nearly 150 comprehensive programs and initiatives, including theater performances, author talks, and art workshops for all ages, spotlighting various aspects of Black heritage, culture and resilience. 

Popular places where you can watch the Big Game in Queens

Feb. 2, 2023 By Tammy Scileppi

Hey, football fans! Game time is fast approaching, and across the city and here in Queens, you can feel the excitement brewing as the two teams prepare to take the field on Super Sunday, Feb. 12. So, kick back and watch the big game, and don’t miss Rihanna’s exciting performance during halftime. 

Borough president hears from community members on budget needs throughout Queens

During a two-day public hearing on the mayor’s 2024 preliminary budget, Queens Borough President Donovan Richards Jr. listened to testimonies from 14 community board representatives, community stakeholders and members of the public on where the money should be spent in Queens. 

The public hearings were held both in-person and via Zoom on Monday, Jan. 30, and Tuesday, Jan. 31, at Queens Borough Hall. The testimonials will be used to develop the Queens Borough Board’s FY24 preliminary budget priorities in the coming weeks. 

‘Limitless possibility’: BP Richards announces community visioning workshops on redevelopment of Creedmoor Psychiatric Center campus in Queens Village

Queens Borough President Donovan Richards Jr. and Empire State Development on Tuesday, Jan. 31, announced the launch of a series of community visioning workshops that will be held to hear input from eastern Queens residents about the redevelopment of the 50-acre Creedmoor Psychiatric Center campus in Queens Village. 

The first community visioning workshop will be held on Thursday, Feb. 2, at 7 p.m. at P.S./I.S. 208 located at 74-30 Commonwealth Blvd. in Glen Oaks.

‘He didn’t deserve to die’: Borough President Richards leads emotional candlelight vigil for Tyre Nichols

Queens Borough President Donovan Richards held a candlelight vigil for Tyre Nichols outside Queens Borough Hall Monday, Jan. 30 after Nichols’ death at the hands of police officers in Memphis, Tenn., made national headlines for the brutality in which the officers beat him.

Almost immediately after news broke about Nichols’ death, the Memphis police officers who beat him to death were fired and charged with murder. The police department released the body cam footage of the fatal beating on Jan. 27, but many people, including some at the vigil, have refused to watch it due to its extremely graphic nature.