NRG, the Houston-based energy company, is refusing to back down on its plans to overhaul its 50-year-old peaker plant in Astoria.

The company said the state’s decision to reject its plan to rebuild its Astoria plant was “short-sighted and politically driven.” Now, it hopes a judge will agree.

NRG Energy has requested an adjudicatory hearing after the New York State Department of Environmental Conservation denied permits sought by the company to replace its 50-year-old plant on 20th Avenue.

“NRG is requesting an adjudicatory hearing related to the New York State Department of Environmental Conservation’s decision to deny an air permit for the Astoria Replacement Project,” Tom Atkins, vice president of development for NRG Energy, said in a statement Friday.

NRG proposed replacing its aging gas and oil-fired turbines with a natural gas-fired plant, but the DEC concluded last month that the plan failed to comply with state climate requirements.

The company maintains that its plan would significantly reduce greenhouse gas emissions coming from its current plant — and that the DEC’s decision was motivated by political interests.

“The DEC’s decision is short-sighted, politically driven, contrary to the plain language of the Climate Leadership and Community Protection Act (CLCPA), as well as both legally and factually flawed,” Atkins said.

Critics of the plan argue that the state should reject the proposal since the plant would still be powered by fossil fuels, noting that natural gas is not clean energy.

NRG, however, has argued that New York City cannot be reliably powered by renewable energy sources alone at this time. In the meantime, the company’s plan would reduce its current carbon footprint at the site with the use of natural gas — as the city moves to a renewable future, it said.

The company added that its peaker plant acts as a backup when other plants — powered by clean energy — are down or unable to produce enough energy to power the city. Therefore, it’s often not in use and emitting pollutants.

“As a backup/standby unit that only operates when there are not enough renewable energy resources available, we will continue to demonstrate the Project is fully consistent with the limits, targets, and goals of the CLCPA and will play a meaningful role in helping New York transition to a zero-carbon electric grid,” Atkins said.

Regardless of the DEC’s decision, NRG will retire the current plant in May 2023 in accordance with the DEC’s energy efficiency laws. The plant will no longer comply with state-level restrictions on nitrogen oxide emissions.

email the author: news@queenspost.com
No comments yet

Leave a Comment
Reply to this Comment

All comments are subject to moderation before being posted.


The reCAPTCHA verification period has expired. Please reload the page.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Recent News

MTA opens three new modernized elevators at the Queens Plaza subway station in Long Island City

The Metropolitan Transportation Authority (MTA) announced the opening of three new modernized elevators at the Queens Plaza E/M/R subway station in Long Island City earlier this month as part of a larger accessibility and safety upgrades throughout the transit system.

The work included a full replacement of the cab and equipment within the cab, shaft and pit, along with two new elevator head houses located at street level. Crews also made modifications to the shaft and pit as needed to allow for new equipment. The elevator machine room and electrical and mechanical equipment received replacements and other modernization efforts for reliability.

Halletts Point esplanade in Astoria opens, reconnecting community to East River waterfront

Aug. 22, 2025 By Bill Parry

When The Durst Organization broke ground on its massive Halletts Point project in Astoria on a cold winter day in January 2016, the speeches were delivered inside a massive brick warehouse that had cut off public access to a stretch of East River waterfront for generations. That warehouse is long gone, demolished and then replaced by two high-rise residential towers, 20 and 30 Halletts Point, which launched leasing earlier this year, and a 58,000-square-foot waterfront esplanade that opened to the public this month.